This section is brought to you in association with Oliveboard, leaders in Test-prep that make it easy for you to prepare across multiple devices. Visit Oliveboard here.
Oliveboard Question of the day
Question: 12 women can complete a work in N days. 7 men can finish the same work in (N+9) days. The time taken by 9 women to complete the work is 2/3 times the time taken by 5 men to complete the work. Find the value of N.
Answer Options:
(1) 18
(2) 21
(3) 25
(4) 28
(5) 24
Solution posted below. Click on the plus sign to view the solution.
Answer and Explanation
Answer key: 2 Solution:
The time taken by 9 women to complete the work is 2/3 times the time taken by 5 men to complete the work.
It means efficiency of 9 women = 3/2 times the efficiency of 5 men
Efficiency of 6 women = Efficiency of 5 men
Let a man do 6k units of work in a day.
Then, a woman does 5k units of work in a day.
12 women can complete the work in N days and 7 men in (N+9) days.
Hence, total work = 12 x 5k x N = 7 x 6k x (N+9)
60kN = 42k(N+9)
60N = 42N + 378
18N = 378
N = 21 days